# No. Funding Programme Local Authority Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Stage 4 Tender Report or Final Turnkey/CALF approval On Site Completed
1 SHIP CONSTRUCTION TURNKEY Carlow Tullow Road, Carlow - Phase 1 24 *N/A Q4-2017
2 SHIP CONSTRUCTION TURNKEY Carlow Tullow Road, Carlow - Phase 2 16 *N/A Q4-2017
3 SHIP CONSTRUCTION TURNKEY Carlow Tullow Road, Carlow - Phase 3 23 *N/A Q4-2017
4 SHIP CONSTRUCTION Carlow The Laurels, Carlow Town 5 *N/A Q3-2017
5 SHIP CONSTRUCTION Carlow Ard na Greine, Tullow 16 *N/A Q4-2017
6 SHIP CONSTRUCTION Carlow Dublin Road, Tullow 21 *N/A Q4-2017
7 SHIP CONSTRUCTION Carlow Bagenalstown 42 *N/A Q4-2017
8 SHIP CONSTRUCTION Carlow Bilboa 2 *N/A Q4-2017
9 SHIP CONSTRUCTION Carlow Hacketstown 4 *N/A Q1-2018
10 SHIP CONSTRUCTION Carlow Mount Leinster Park, Carlow 4 *N/A Q4-2017
11 SHIP CONSTRUCTION Carlow Myshall 4 *N/A Q1-2018
12 SHIP CONSTRUCTION Carlow Pound Lane, Borris 4 *N/A Q3-2017
13 SHIP CONSTRUCTION Carlow Rathvilly 10 *N/A Q2-2017
14 SHIP CONSTRUCTION Carlow Moneybeg, Bagenalstown 24 *N/A Q3-2017
15 SHIP CONSTRUCTION Carlow Paulville, Tullow (SRD) 1 *N/A Q3-2017
16 SHIP CONSTRUCTION Carlow Maryborough St., Carlow 5 *N/A Q1-2018
17 SHIP CONSTRUCTION Carlow Drumin, St. Mullins (SRD) 1 *N/A Q4-2017
18 CAS CONSTRUCTION Carlow Mill Race Court, Carlow Town 14 Cluid Housing Association Stage 1 approved in Q3-2015, outline design and costs are now being prepared.
19 CAS CONSTRUCTION Carlow Royal Oak Road, Bagenalstown 6 Respond Stage 3 approved in Q4-2017, the scheme is now being tendered.
20 CAS CONSTRUCTION Carlow Ballincarrig, Wexford Road 6 Tintean Housing Association Ltd Q4-2016
21 CALF CONSTRUCTION TURNKEY Carlow Sleaty Street, Graigcullen, Carlow 26 Cluid Housing Association Q1-2018
22 CALF CONSTRUCTION TURNKEY Carlow Barrett Street, Bagnalstown 10 Tintean Housing Association Q1-2018
23 CALF CONSTRUCTION TURNKEY Carlow River Court, Carlow 1/4* 10 Co-operative Housing Ireland Scheme approved for funding Q1 - 2018
24 CALF CONSTRUCTION TURNKEY Carlow River Court, Carlow 2/4 16 Co-operative Housing Ireland Scheme approved for funding Q1 - 2018
25 CALF CONSTRUCTION TURNKEY Carlow Browneshill Wood, Browneshill Road, Chapelstown, Carlow 1/1 59 Tath Housing Association Ltd Q1-2018