# Reference Title Electoral Area Road Classification Contractors Name Asset Type Work Description Status of Works Final Actual Area Planned Start Date Completion Date Roads Listing Surface Type Re-Surfacing Materials X Co-ordinate Y Co-ordinate
1 Mount Street Lower - Repair and Resurfacing contract South East Traffic Impact 4 Arkil Roadway Asphalt Repairs and Resurfacing works Complete 6625m2 2012-09-06T00:00:00 2012-05-08T00:00:00 MOUNT STREET LOWER DUBLIN 2;#2644 Bituminous;#2 Bituminous;#2 317060470.42 233446311.67
2 NC, NW & C Speed Ramps Contract Northside Various KN Network Services Traffic Calming Measure Resurface and Reconstruct Traffic Calming Features Planned 2,011m^2 of 35mm resurfacing 1,922m^2 of 50mm Geogrid resurfacing 30m^2 of 100mm Reconstruction 89m^2 of 500mm deep Reconconstruction 46No. Geo Reference Locations 2012-04-23T00:00:00 2012-08-08T00:00:00 CLUNE ROAD FINGLAS EAST DUBLIN 11;#935;#MCKEE ROAD FINGLAS EAST DUBLIN 11;#2495;#SYCAMORE ROAD FINGLAS EAST DUBLIN 11;#3726;#TOLKA ESTATE FINGLAS EAST DUBLIN 11;#3855;#GROVE PARK ROAD FINGLAS EAST DUBLIN 11;#1840;#GROVE ROAD FINGLAS EAST DUBLIN 11;#1841;#BALBUTCHER LANE BALLYMUN DUBLIN 11;#213;#CHARLEMONT DUBLIN 9;#745;#COOLOCK VILLAGE CLOSE COOLOCK DUBLIN 5;#997;#MARYFIELD CRESCENT ARTANE DUBLIN 5;#2459;#HAZELWOOD DRIVE ARTANE DUBLIN 5;#1935;#CELTIC PARK ROAD BEAUMONT DUBLIN 9;#728;#COLLINS PARK BEAUMONT DUBLIN 9;#956;#GREENCASTLE ROAD BONNYBROOK DUBLIN 17;#1777;#WHITWORTH ROAD DRUMCONDRA DUBLIN 9;#4044;#CONNAUGHT STREET PHIBSBOROUGH DUBLIN 7;#965;#BOTANIC AVENUE DRUMCONDRA DUBLIN 9;#465;#CARNLOUGH ROAD CABRA WEST DUBLIN 7;#646;#BROOMBRIDGE ROAD CABRA DUBLIN 7;#540 Imprint Asphalt;#8;#Bituminous;#2;#Geotextile;#11 Bituminous;#2
3 South East Asphalt Contract (2012) South East (None) Sierra Communications Ltd Footway & Roadway Asphalt repairs and Resurfacing on Bull Alley St, The Appian Way, Bushes Lane /Grosvenor Villas and Fortfield Gardens/Fortfield Terrace. Concrete footway repairs on Fortfield Gardens and Fortfield Terrace. Concrete carriageway repairs on Bushes Lane. Concrete channel construction on Bushes Lane. Underway 2012-10-04T00:00:00 THE APPIAN WAY RANELAGH DUBLIN 6;#3781;#BULL ALLEY STREET DUBLIN 8;#550;#BUSHES LANE RATHGAR DUBLIN 6;#562;#GROSVENOR VILLAS RATHGAR DUBLIN 6;#1832;#FORTFIELD GARDENS RATHMINES DUBLIN 6;#1518;#FORTFIELD TERRACE RATHMINES DUBLIN 6;#1520 Bituminous;#2;#Concrete Paving;#4 Bituminous;#2;#Concrete Paving;#4
4 North Central Footpath Contract 2012-1 North Central Traffic Impact 3 KN Network Services Footway Localised footpath repairs from hazard register database Planned KILBARRACK ROAD KILBARRACK DUBLIN 5;#2125;#KILMORE ROAD ARTANE DUBLIN 5;#2158;#OSCAR TRAYNOR ROAD COOLOCK DUBLIN 5;#2864;#BEAUMONT ROAD BEAUMONT WOODS DUBLIN 9;#304;#GRACE PARK ROAD DRUMCONDRA DUBLIN 9;#1704 Concrete Paving;#4 In Situ Concrete;#1
5 California Hills Fencing Contract South Central Traffic Impact 4 KN Network Services Roadway Reinstatement of fence along the Kylemore Rd and Chapelizod By Pass. Complete 2012-06-20T00:00:00 2012-07-17T00:00:00 KYLEMORE ROAD BALLYFERMOT DUBLIN 10;#2211 Miscellaneous;#9 Miscellaneous;#9 309479.29 234595.12
6 SE and SC Ramps Contract Various Siac Bituminous Products Ltd Roadway Resurfacing of ramps in the SE and SC Areas Complete 1428m2 in SC Area 2210m2 in SE Area 2012-07-16T00:00:00 2012-10-25T00:00:00 Bituminous;#2 Bituminous;#2
7 South Quays. Footpath Reconstruction South East Traffic Impact 5 KN Network Services Footway Reconstruct concrete paving slabs. Underway 2012-07-08T00:00:00 CRAMPTON QUAY DUBLIN 2;#1038;#WELLINGTON QUAY DUBLIN 2;#3993 Concrete Paving;#4 Concrete Paving;#4 315693.72 234230.73
8 Dame Street Footfath Reconstruction South East Traffic Impact 5 KN Network Services Footway Reconstruction of the footpath on the South side of Dame St between Palace St and Trinity Street. The project involves resetting the existing granite kerbs and reconstructing the footpath with concrete paving slabs. Planned DAME STREET DUBLIN 2;#1120 Concrete Paving;#4 Concrete Paving;#4 315685.85 234033.11
9 NTA Funded Carriageway Renewal Works Package 5a South East Traffic Impact 4 Siac Bituminous Products Ltd Roadway The works consist in Package 5a, 2 No. sections of road. In total, the works comprise 255m2 bituminous carriageway surface course resurfacing, 18,780m2 of surface course, binder course and geogrid (100mm depth) and 1,447m2 reconstruction of Pavement. The works for Package 5a were be carried out at the following locations: Rathgar Road from the junction with Terenure Road East/Highfield Road and the junction with Grosvenor Road (1150m in length) Rathmines Road Lower between the junction with Military Road/Richmond Hill and the junction with Harrington Street/Harcourt Road (650m in length) Complete In total, the works comprise 255m2 bituminous carriageway surface course resurfacing, 18,780m2 of surface course, binder course and geogrid (100mm depth) and 1,447m2 reconstruction of Pavement. 2012-08-19T00:00:00 2012-09-27T00:00:00 RICHMOND STREET SOUTH DUBLIN 2;#3181;#RATHMINES ROAD LOWER RATHMINES DUBLIN 6;#3120;#RATHGAR ROAD RATHGAR DUBLIN 6;#3113 Bituminous;#2;#Ecoflex;#5 Bituminous;#2;#Ecoflex;#5
10 North West Area Contract North West Various Richard Nolan Civil Engineering Footway & Roadway St Helena's Road Carriageway reconstruction( excavation 500mm depth, stone laying, bituminous base, binding course and surface course) St Pappins Road& Shanowen Road Footpath Reconstruction Complete 2012-06-15T00:00:00 2012-08-31T00:00:00 SAINT HELENA'S ROAD FINGLAS SOUTH DUBLIN 11;#3325;#SAINT PAPPIN ROAD GLASNEVIN DUBLIN 11;#3403;#SHANOWEN ROAD SANTRY DUBLIN 9;#3537 Bituminous;#2;#Concrete Paving;#4 Bituminous;#2;#Concrete Paving;#4